The network shows cable links between office areas. Each edge label gives the installation cost in dollars. Compare paths from Studio to Server

Weighted network. Vertices in listed order: [Design | Finance | Server | Studio | Meeting]. Full edge list: Server–Meeting ($476); Studio–Finance ($81); Design–Studio ($87); Meeting–Design ($478); Finance–Server ($472); Studio–Server ($480); Design–Server ($83).$476$81$87$478$472$480$83DesignFinanceServerStudioMeeting
(a)3 marks

Find the complete route total for every named route

(b)1 mark

Using the route totals, choose the shortest route from Studio to Server

(c)1 mark

Calculate the least possible total installation cost for a path from Studio to Server