Consider this activity-on-arrow network for a garden installation. Nodes are events. Solid arrows are activities and dashed arrows are zero-duration dummy activities. Each edge label gives the activity id and duration in days

Activity-on-arrow network. Nodes are events. Event order: [4 | 6 | 7 | 5 | 9 | 10 | 8]. Full activity list: A: 4 to 6, 13 days, solid; B: 6 to 5, 3 days, solid; C: 4 to 7, 2 days, solid; D: 7 to 5, 8 days, solid; E: 5 to 9, 11 days, solid; F: 9 to 8, 5 days, solid; G: 5 to 10, 4 days, solid; H: 10 to 8, 7 days, solid.A (13 days)B (3 days)C (2 days)D (8 days)E (11 days)F (5 days)G (4 days)H (7 days)46759108
Complete activity data
ActivityFrom eventTo eventDuration (days)Arrow
A4613activity (solid)
B653activity (solid)
C472activity (solid)
D758activity (solid)
E5911activity (solid)
F985activity (solid)
G5104activity (solid)
H1087activity (solid)
(a)1 mark

What is the EST of activity H?

(b)1 mark

How much total float does activity H have?