Complete a critical path analysis
The activity-on-arrow network models community event preparation. Nodes are events. Solid arrows are activities and dashed arrows are zero-duration dummy activities. Each edge label gives the activity id and duration in days
| Activity | From event | To event | Duration (days) | Arrow |
|---|---|---|---|---|
| E | 15 | 17 | 2 | activity (solid) |
| F | 17 | 16 | 13 | activity (solid) |
| G | 15 | 18 | 2 | activity (solid) |
| H | 18 | 16 | 9 | activity (solid) |
| I | 16 | 20 | 3 | activity (solid) |
| J | 20 | 19 | 3 | activity (solid) |
| K | 16 | 21 | 2 | activity (solid) |
| L | 21 | 19 | 9 | activity (solid) |
| M | 16 | 22 | 3 | activity (solid) |
| N | 22 | 19 | 2 | activity (solid) |