Translate between precedence data and an activity network
Consider the activity-on-arrow data for a workshop refit. Nodes are events. Solid arrows are activities and dashed arrows are zero-duration dummy activities. The precedence relation records which activities must finish before another activity starts
| Activity | Immediate predecessors |
|---|---|
| D | C |
| C | none |
| G | F |
| F | C |
| E | D |
| Activity | Duration (days) |
|---|---|
| D | 3 |
| C | 4 |
| G | 2 |
| F | 2 |